Browse PIP Practices

Review the most up-to-date collection of PIP Practices. Most recently published practices are listed first. Search key terms or filter by discipline to narrow the list.

Found 591 Results
Icon for CSA
CSA
ARS08111

Standard Steel Doors and Frames Supplier Specification

Abstract ↓

This Practice provides supplier with requirements for all material, fabrication, finishes, and delivery of standard steel doors and frames.This Practice applies recommendations of the Steel Door Institute (SDI) of Westlake, Ohio.Comment It is recommended that SDI-108 be used to prepare contract documents.

May 2018
Complete Revision
Icon for CSA
CSA
ARS08112

Standard Steel Doors, Frames and Related Hardware Installation Specification

Abstract ↓

This Practice provides constructor with requirements for installing standard steel doors, frames and related hardware. It applies recommendations of the Steel Door Institute (SDI) of Westlake, Ohio and the Door and Hardware Institute (DHI) of Chantilly, Virginia. This Practice does not include requirements for field-applied finish painting.

May 2018
Complete Revision
Icon for CSA
CSA
ARS08710

Standard Steel Door Hardware Supplier Specification

Abstract ↓

This Practice provides supplier with requirements for all material, fabrication, finishes, and delivery of standard steel door hardware. This Practice is written without reference to specific manufacturers, brand names, or model numbers. Industry standards from American National Standards Institute (ANSI) and Builders Hardware Manufacturers Association (BHMA) are used to specify performance and quality requirements for pieces of hardware.Hardware for aluminum entrance doors or specialty doors is not included.

May 2018
Complete Revision
Icon for I/E
I/E
ELSMC11

Medium-Voltage Motor Control Center Specification

Abstract ↓

​This Practice describes the requirements for the design, materials, fabrication, inspection, testing, documentation, and shipment of metal-enclosed, NEMA Class E2 controllers (2001V to 7200V). This equipment is used for the supply, control, and protection of medium-voltage motors.

April 2018
Complete Revision
Icon for I/E
I/E
ELEGL01

Overall Electrical One-Line Diagram Guideline

Abstract ↓

This Practice is a guideline for developing Overall Electrical One-Line Diagrams (OEOLDs) by engineers and designers. It covers the generation of new OEOLDs and may not apply to the revision of existing OEOLDs.This Practice applies to one-line diagrams that fit the definition of an OEOLD in Section 3. This Practice uses ANSI/IEEE 315 - IEEE Graphic Symbols for Electrical and Electronics Diagrams and IEEE C57.12.80 - IEEE Standard Terminology for Power and Distribution Transformer symbols.The main purpose of an OEOLD is to provide an initial view of the electrical system for use in early design discussions. Then, the OEOLD can be updated as the project develops and kept current to provide a reference document that shows a high level view of the overall electrical system. As a secondary purpose and function the symbols provided for use in a OEOLD are intended to provide basic information. The basic information is shown in visible fields by default. Many OEOLD symbols have hidden or invisible fields that provide extra information or details. The invisible or hiddens fields can be changed to be visible based on owner requirements. This Practice can be applied to CAD systems used for developing OEOLDs, and is not supplier, hardware, or software specific. Electronic native files for the text, symbols, and cover sheets are available from PIP for use in CAD systems and have been developed in AutoCAD 2015. While the symbols can also be developed in Microstation DGN files, the functionality from AutoCAD may not be available in Microstation. Development of project-specific legend sheets is recommended using the PIP native files as a starting point. Additions and/or deletions are permitted to meet project requirements. Drawing borders and title blocks can be altered to be project specific.The guidelines in this Practice provide a balance between showing all data on OEOLDs and making OEOLDs legible and easy to read. Although this Practice describes major components in the electrical system, specific applications may require additional or alternative components. Determinations concerning fitness for purpose and matters of application of the Practice to a particular project or engineering situation should not be made solely on the information contained in this Practice.The OEOLD symbols included in the Appendices of this Practice are not intended to recommend specific design details or requirements. An example OEOLD is included to provide an illustration of how the elements of this Practice are combined into an OEOLD.

April 2018
New Practice
Icon for Process
Process
PIE001

Process Flow Diagram Documentation Guidelines (Universally Applicable)

Abstract ↓

This Practice provides general guidelines for the format and content of Process Flow Diagrams (PFDs) for process and utility systems.This Practice covers the development of new PFDs and does not apply to existing PFDs developed before the adoption of this Practice.The Practice applies to all diagrams that fit the definition of a PFD in Section 3.This Practice can be applied to any CAD system used for developing PFDs and is not vendor, hardware, or software specific.Although this Practice provides general guidelines for the development of PFDs, individual applications may require differing approaches than those recommended in this Practice. Determinations concerning fitness for purpose and matters of application of the Practice to a particular project or engineering situation should not be made solely on the information contained in this Practice.Example PFDs in the Appendixes of this Practice are not intended to recommend specific design details or requirements, but are included to provide illustrations of various options available to the user.

January 2018
New Practice
Icon for I/E
I/E
PCCCV003

Remotely Actuated On-Off Valves Selection Criteria

December 2017
Technical Revision
Icon for I/E
I/E
PCECV003

Guidelines for Application of Remotely Actuated On-Off Valves

Abstract ↓

​This Practice describes guidelines and background information for the application of remotely activated on-off valves. This Practice includes process application, valve and actuator selection, material selection, ancillary equipment requirements, and testing of remotely activated on-off valves (e.g., 2-way, 3-way, 4-way, etc.).This Practice covers non-throttling applications. Throttling applications are considered to be control valves and are covered in PIP PCECV001 and PIP PCCCV001. However, remotely activated on-off valves have many similarities with control valves (e.g., body configuration, materials of construction, internals, etc.). Therefore, this Practice should be used in conjunction with PIP PCECV001.

December 2017
Technical Revision
Icon for Mechanical
Mechanical
CTSL1000

Application of Internal Linings (Universally Applicable)

Abstract ↓

​This Practice provides requirements for installing industrial linings. This Practice describes the general requirements for surface preparation, environmental control, and the installation and inspection of liquid-applied internal linings to metal substrates. This Practice does not cover sheet linings and application of linings to piping.

December 2017
Complete Revision
Icon for Mechanical
Mechanical
INTG1000

Insulation Inspection Checklist

Abstract ↓

This Practice provides a checklist for use by individuals responsible for ensuring the quality and completeness of an insulation job. This Practice describes the requirements for inspecting insulation by providing an Insulation Inspection Checklist, PIP INTG1000-F. The checklist is designed to apply to both cold and hot insulation systems as well as large-scale projects and individual items. As a result, there are specific items on the checklist that may not apply to all projects.Each section has a line for ranking workmanship. Because workmanship is somewhat subjective, ranking is provided.Comment sections are provided where appropriate.This Practice assumes that individuals charged with making the inspections are experienced in the design and installation of insulation systems and are well-acquainted with the PIP Insulation Practices.The checklist does not provide sufficient information to act as a stand-alone document that would allow an inexperienced person to function as an inspector.

October 2017
Reaffirmation
Icon for Mechanical
Mechanical
INSC1000

Cold Service Insulation Materials and Installation Specification

Abstract ↓

This Practice provides requirements for materials and installation of cold service insulation systems. This Practice describes requirements for cold service insulation materials and accessories, storage and handling of materials, insulation application, extent of insulation, and documentation on the external surfaces of piping and equipment, ambient to -179°C (‑290°F).

October 2017
Complete Revision
Icon for I/E
I/E
ELILS000

Lighting and Receptacle Installation Details for Class I, Division 2, Class II, Division 2, and Unclassified Areas

Abstract ↓

​This Practice provides installation details for luminaires and receptacles located in Class I, Division 2 areas, Class II, Division 2 areas, and unclassified areas. This Practice describes the basic assumptions used in developing these details and provides guidelines for their use.Installation details for Class I, Division 1 and Class II Division 1 areas are excluded from the scope of this Practice.

August 2017
New Practice
Icon for CSA
CSA
STE01100

Constructability Design Guide

Abstract ↓

This Practice provides engineers and designers with guidelines for improving the constructability of a project.This Practice describes guidelines for improving constructability of civil, structural, and architectural components of a project. This Practice provides guidelines for grass root projects, revamp projects, and turnarounds.

September 2016
Complete Revision
Icon for CSA
CSA
CVS02005

Topographic and Plant Surveys Specification

Abstract ↓

​This Practice in conjunction with PIP CVS02005-F - Survey Checklist describes the requirements for quality control, permits, deliverables, and execution for topographic and plant surveys. In case of conflict, the Survey Checklist supersedes this Practice.

April 2016
Complete Revision
Icon for CSA
CSA
CVS02010

Geotechnical Engineering Investigation Specification

Abstract ↓

This Practice describes the minimum requirements for a geotechnical engineering investigation including subsurface exploration, field and laboratory testing, analyses, and preparation of reports that present geotechnical engineering recommendations for design and construction. This Practice does not include requirements for an environmentally-related investigation or analysis.

March 2016
Complete Revision
Icon for CSA
CSA
ARC01015

Architectural and Building Utilities Design Criteria

Abstract ↓

This Practice describes the minimum requirements for the design of buildings. This Practice is intended to be used in conjunction with PIP ARC01016 - Building Data Sheet, PIP CVC01017 - Plant Site Data Sheet, and PIP STC01015 - Structural Design Criteria. This Practice does not apply to open or partially enclosed industrial structures.

December 2014
Complete Revision
Icon for CSA
CSA
ARC01016

Building Data Sheet

Abstract ↓

This Practice is intended to be used in conjunction with PIP ARC01015 - Architectural and Building Utilities Design Criteria, PIP CVC01017 - Plant Site Data Sheets, and PIP STC01018 - Blast Resistant Building Design Criteria. These data sheets contain architectural, HVAC, electrical, fire protection, plumbing, and communication information that may be conveyed from the owner to the project design team or from the project design team leaders to the team design members. This data may be provided by the owner or developed by the project design team and approved by the owner.

December 2014
Complete Revision
Icon for CSA
CSA
STC01018

Blast Resistant Building Design Criteria

Abstract ↓

This Practice provides structural design criteria for blast resistant buildings. This Practice describes the minimum requirements for the design of permanent (non-temporary) blast resistant buildings including requirements for selection of structural systems, analysis methods, and design of ancillary items such as doors and openings. This Practice also contains design criteria for non-structural items (e.g., suspended architectural or electrical items, HVAC ductwork, etc.) that could pose a hazard to the occupants of blast resistant buildings.

October 2014
Complete Revision
Icon for I/E
I/E
ELSMT01GD

Data Sheet for IEC AC Squirrel Cage Induction Motor (1000 Volts and Below)

Abstract ↓

This data sheet describes the requirements for manufacturing and testing AC squirrel cage induction motors, as discussed in PIP ELSMT01G - IEC AC Squirrel Cage Induction Motor Specification (1000 Volts and Below).

July 2013
New Practice
Icon for Mechanical
Mechanical
INIC1000

Cold Insulation Installation Details

Abstract ↓

This Practice provides details for installing cold insulation systems on piping, valves, horizontal and vertical vessels, and heat exchangers.

October 2012
Editorial Revision

Date not available
Update type not available

Learn More About PIP Practices